After a 4-1/2 hour joint meeting, the Board of the Mass Department of Transportation and the Fiscal and Management Control Board of the MBTA voted unanimously to continue the Green Line Extension with conditions: Staff are to submit redesign and revised materials to the Federal Transit Authority. Staff are to prepare a revised finance plan suggesting how to make up the remaining $73M shortfall. Staff are to report to board: Strategy and progress for hiring a management team for the GLX project and for addressing ongoing T management issues. Recommendations for advancing project while FTA
More…
Read Full Story from Somerville Voices http://www.somervillevoices.org/2016/05/09/development-and-zoning/5916-massdot-and-control-board-vote-to-continue-glx-with-conditions/
This article by David Dahlbacka originally appeared on somervillevoices.org on May 10, 2016 at 02:31AM